YANGJIANG-4

Operational


Reactor Details

Reactor Type Model Owner Operator
PWR
CPR-1000
Yangjiang Nuclear Power Company
Yangjiang Nuclear Power Company
Reference Unit Power (Net Capacity) Design Net Capacity Gross Capacity Thermal Capacity
1000 MWe
1000 MWe
1086 MWe
2905 MWt
Construction Start Date First Criticality Date
17 Nov, 2012
30 Dec, 2016
First Grid Connection Commercial Operation Date
08 Jan, 2017
15 Mar, 2017

LifeTime Performance

Electricity Supplied Energy Availability Factor Operation Factor Energy Unavailability Factor Load Factor
53.00 TW.h
92.2 %
88.4 %
7.8 %
88.2 %
Lifetime performance calculated up to year 2023

Operating History

Year Electricity Supplied
[GW.h]
Reference Unit Power
[MW]
Annual Time On Line
[h]
Operation Factor
[%]
Energy Availability Factor
[%]
Load Factor
[%]
Annual Cumulative Annual Cumulative
2017 6759.710 1000 6353 86.5 90.7 90.7 90.3 90.3
2018 6591.930 1000 6695 76.4 83.4 86.7 75.2 82.1
2019 6915.910 1000 7164 81.8 91.9 88.5 79.0 81.0
2020 7954.620 1000 8216 93.5 97.0 90.8 90.6 83.5
2021 7977.130 1000 7880 90.0 89.4 90.5 91.1 85.0
2022 7820.950 1000 7927 90.5 92.9 90.9 89.3 85.8
2023 8978.180 1000 8760 100.0 100.0 92.2 102.5 88.2
Performance indicators are calculated from the Commercial Operation Date.


Above data generated by the PRIS database. Last update on 2024-07-02